Scenario 1

The Leadership Development contract has been signed and you are working with the Department’s contract manager and the contractor to program a number of training days. A colleague has just informed you that there may be some problems with the Cairns office. He has heard that they are unhappy that the Leadership Development programme has been organised by the Brisbane office. Apparently, management and staff in Cairns have been discussing the idea of pulling out of the Leadership Development programme you have tendered and contracted for and are considering running their own. Your colleague thinks that they may even have been talking to a couple of Cairns based providers to get ideas and preliminary quotes.

Answer the following questions: